Tuck Creek Erosion Control Municipal Class Environmental Assessment

Project Details
  • Location
    Burlington, ON
  • Project Contact
    • Mark Bassingthwaite
  • Client
    City of Burlington
  • Completion

    Ongoing

Project Highlights

Cole Engineering completed a Schedule ‘B’ Municipal Class Environmental Assessment to investigate existing erosion problems and determine erosion protection alternatives for a stretch of Tuck Creek between Billings Court (south of QEW) to Harvester Road. The scope of the project includes identification of construction access, potential land requirements, erosion control methodology and completion of a public consultation program including a public information centre. Agencies consulted include First Nations, Conservation Halton and Ministry of Natural Resources. The preferred alternative was to implement bio-engineering solutions at select locations within the creek. Proposed improvements include a variety of erosion control improvements as well as the removal of failing gabion walls throughout the study area.